Rarotonga, 2010

Simon's Megalomaniacal Legal Resources

(Ontario/Canada)

ADMINISTRATIVE LAW | SPPA / Fairness (Administrative)
SMALL CLAIMS / CIVIL LITIGATION / CIVIL APPEALS / JUDICIAL REVIEW / Practice Directives / Civil Portals

Home / About / Democracy, Law and Duty / Something Big / Testimonials / Conditions of Use

Civil and Administrative
Litigation Opinions
for Self-Reppers

Simon's Favourite Charity -
Little Friends Lefkada (Greece)
Cat and Dog Rescue


TOPICS


Construction - Judicial Review

. Caledon (Town) v. 2220742 Ont. Ltd. o/a Bronte Construction

In Caledon (Town) v. 2220742 Ont. Ltd. o/a Bronte Construction (Div Court, 2024) the Divisional Court considered a JR of a Construction Act adjudication.

Here the court considers the 'prompt payment' and related JR provisions of Construction Act:
Limited Jurisdiction of this Court

[56] As noted by this court in SOTA Dental Studio Inc. v. Andrid Group, 2022 ONSC 2254, para. 9 (Div. Ct.):
The whole point of these provisions is to require prompt payment to avoid the consequences of disruptions to construction projects of brinksmanship over disputes that arise. The prompt payment provisions are based on similar provisions introduced in the United Kingdom more than a decade ago. They provide for a quick and relatively informal adjudication, by an adjudicator experienced in construction law disputes. The decision is without prejudice to the parties contesting issues between them at the end of the project. It triggers an obligation on the part of the payee to make its payments to its subcontractors, suppliers and workers. Effective implementation of these provisions is intended to reduce terminations (by payors) and work cessations (by payees) in the midst of construction, either of which can cause cascading losses down the construction pyramid. The obligation to pay, and to pay promptly, when ordered to do so, is fundamental to the scheme of the prompt payment provisions.
[57] The bases on which the court may intervene on an application for judicial review reflects the nature of the award made by an adjudicator: it is an interim award, without prejudice to the parties, and is to be made swiftly following a prescribed prompt process. The court affords a high degree of deference to an adjudicator’s decision and will intervene only in limited circumstances.

[58] The complete text of s. 13.18(5) of the Act states:
The determination of an adjudicator may only be set aside on an application for judicial review if the applicant establishes one or more of the following grounds:

1. The applicant participated in the adjudication while under a legal incapacity.

2. The contract or subcontract is invalid or has ceased to exist.

3. The determination was of a matter that may not be the subject of adjudication under this Part, or of a matter entirely unrelated to the subject of the adjudication.

4. The adjudication was conducted by someone other than an adjudicator.

5. The procedures followed in the adjudication did not accord with the procedures to which the adjudication was subject under this Part, and the failure to accord prejudiced the applicant’s right to a fair adjudication.

6. There is a reasonable apprehension of bias on the part of the adjudicator.

7. The determination was made as a result of fraud.
. Jamrik v. 2688126 Ont. Inc.

In Jamrik v. 2688126 Ont. Inc. (Div Court, 2024) the Divisional Court allowed a JR against a Construction Act (CA) adjudicator's 'prompt payment' decision that "the contract was not “completed” within the meaning of the Construction Act".

Here the court considers a Construction Act JR [under CA s.13.18(1)]:
[7] An application for judicial review of an adjudicator’s decision lies to this court with leave: Construction Act, s.13.18(1). Leave was granted for this application on September 25, 2023: Jamrik v. 2688126 Ont. Inc. o/a Turnkey Construction, 2023 ONSC 5362 (Div. Ct.).





CC0

The author has waived all copyright and related or neighboring rights to this Isthatlegal.ca webpage.




Last modified: 26-08-24
By: admin